MISO Distribution Hardening — 380 miles
A 380-mile distribution hardening program across a MISO utility’s territory. We are replacing weak poles, converting overhead lines to underground in certain areas, adding wildlife protection, and installing automated switches. Six full-time crews on a 30-month schedule.
- Client
- MISO distribution utility
- Region
- Lower Midwest (MISO)
- Duration
- 30 month program
- Voltage
- 12.47 kV · 380 mi
- Status
- In Progress
Project details.
The challenge we walked into.
A MISO distribution utility needed to strengthen 380 miles of older 12.47 kV distribution circuits — driven by reliability targets and grid modernization filings with their regulator. The work had to happen on a schedule the regulator approved, with strict customer-notice and outage-minimization requirements.
How we approached the work.
- 01
Six full-time crews
Six crews assigned to the program full-time, with two additional flex crews available during peak windows. A predictable schedule meant predictable rate-case filings for the utility.
- 02
Multiple types of work
Composite pole replacement on the highest-risk sections, underground conversion in dense neighborhoods, and wildlife protection across the whole program.
- 03
Strict customer notice
Outage scheduling built around the customer-notice windows the regulator required. Zero notice violations across the program to date.
What the client got.
Year-1 work (130 miles) closed on schedule. Year-2 (140 miles) finished 12 days ahead of schedule. Year-3 (110 miles) is in progress with the same full-time crew team.
Similar work.
Have a project that looks like this one?
We respond within two business days. For emergency, federal, and large industrial work, within four hours.